On Track Button Not Working Randomly Grr
If you have played around with the status date in the Project file and the 'mark on track' button does not work anymore to calculate % work complete, you need to reset the Status date to show current date.
Type NA in the date field and it should reset it for you.
BOOM Easy as that!
Update: MS Project 2013 Screen shots below